Continuous, standby and reserve duty
The same alternator can be quoted against three different duties, and the duty changes what the rating means. A buyer who does not name the duty will get a rating that is right for a machine they did not order.
The same machine, three promises
A machine is not sold as a machine. It is sold as a machine doing a particular job, and the rating means something different in each case.
That is why a rating quoted without a duty is not a rating. The figure is the same in the catalogue, but the promise behind it changes with how the machine is expected to be used.
Continuous duty
The machine runs for long stretches and is expected to keep running. Heat builds up in the winding over hours rather than minutes, and the rating reflects that. It is the duty for a generator that is the primary supply, not a backup.
Continuous rating usually comes with an allowance for a limited overload for a limited period, within a limited number of occurrences over the life of the machine. The allowance is part of the duty and it has to be understood, not assumed.
Standby duty
The machine sits idle and starts when it is needed. Its rating reflects the fact that it will run hard, at a higher ambient temperature than the reference, and for a shorter period than a continuous machine would.
This is the duty of the emergency generator at a data centre, a hospital, a commercial building or a plant that has to keep running when the grid does not.
Reserve duty
A third rating exists for machines that are not the first machine to run. Where several sets work together, one carries the load and the others wait. The waiting machines have a duty of their own, and it is not the same as either of the other two.
Why the ambient reference differs between them
Each duty is rated against the ambient temperature the machine is expected to meet while doing it. A machine that sits next to other equipment in a plant room during a summer is in a different place from one that is in a cool hall, and the duty is what says which of those two situations the rating was set for.
This is also why a machine cannot simply be moved from one duty to another. The rating was made for a condition; change the condition and the rating no longer says what you need it to say.
How to state it
- Continuous if the machine runs as the main supply, or for long periods by design.
- Standby if it starts on failure and carries the load until the grid returns.
- Reserve if it shares the load with other sets that are also waiting.
And if the set does both, say so. A standby set that also does a weekly test run is not the same machine as one that only ever runs in an emergency, and the rating is written for one or the other.